Fiscal Year 2026-2027 Budget and Employee Step Plan
The first months of the fiscal year show healthy sales tax and steady revenues, though property tax money hasn't flowed in yet. Spending outpacing revenue now is normal and should balance out over the year.
Sewer Moratorium and Capacity Allocation Framework
Multiple applicants — Pooch Playhouse, Signature Homes, SHIP West, Keystone Outdoors, and Mahlon Moore Road — are competing for scarce sewer capacity or on-site treatment approvals while the city operates under a TDAC consent order and sewer moratorium. The board is wrestling with how to interpret its own ordinance and whether building expansions qualify for discretionary allocations.
Project Blue and Spring Hill Commerce Center Infrastructure
The developer wants to mass-grade Project Blue's southern parcel, removing most existing trees including 65 significant trees. Staff flagged a conflict with the pattern book's clear-cutting ban and proposed a surety for replacement trees — but the mayor warned the 'tree bank' it would fund doesn't exist yet.
Internal Control Manual and Financial Policies
The committee updated internal controls, grant thresholds, and debt policies to ensure smooth city operations and compliance with auditor recommendations.
Jim Warren Road and Port Royal Road Improvements
Drivers face major traffic jams and queuing on Port Royal Road approaching Saturn Parkway, especially during Sunday church dismissals. The city uses manual police overrides and is reviewing signal timing to ease the bottlenecks.
Water Division Capital Improvement Projects (Westview and Williamsburg)
Aldermen expressed anxiety over unknown long-term costs for water and sewer expansion projects, estimated around $200 million, and requested clearer monthly financial tracking and funding plans for capital projects during the moratorium.
Wastewater Reclamation Plant Dewatering Program Re-evaluation
The city decided to cancel a planned $28 million standalone centrifuge project after operational improvements at the wastewater plant proved successful. Officials plan to roll dewatering into the progressive design-build program, saving millions while maintaining plant performance.
Nelly's Italian Cafe Sewer Capacity Allocation Request
Local business owners raised concerns about equitable sewer capacity allocation under Ordinance 25-29, stating that commercial developers are withholding capacity from out-parcel buyers.
Advanced Purification Pilot & Water Infrastructure
The city is moving forward with advanced water purification pilot designs and TDEC agreements to bolster long-term water treatment capacity.
Sawgrass and Sawgrass West Subdivision Infrastructure Deficiencies
Homeowners from Sawgrass and Sawgrass West told the board about massive builder defects left by Lennar, including broken irrigation, cracked pools, fire code violations in riser rooms, and a single master water meter forcing neighbors to pay each other's bills. The board responded by delaying bond releases for two phases to allow staff to investigate.
Wastewater Treatment Plant Solids Removal
City staff reported serious operational issues with belt presses at the wastewater reclamation plant, requiring an emergency expense of $400,000 to $500,000 to pump out accumulated solids.