Oak Hill water project change order
Summary
The Oak Hill water system and elevated tank projects are wrapping up with net decreases, but the contractor Phoenix Fabricators was terminated for not finishing paperwork, delaying grant closeout.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 17, 2026.
Impact analysis
Change orders reduce costs by about $55,800 combined; ARPA reimbursement deadlines hit end of September.
Utility customers and taxpayers, since grant funds and lower costs offset project expenses.
Mentions & discussions (3)
City Council Meeting - Aug 17, 2026
The Oak Hill water system and elevated tank projects are wrapping up with net decreases, but the contractor Phoenix Fabricators was terminated for not finishing paperwork, delaying grant closeout.
City Council Meeting - May 4, 2026
The council added back 2,000 feet of 16-inch water line that was cut from the project earlier when money was tight — a $501,797.50 addition covered entirely by grant clawbacks and under-budget grants.
City Council Meeting - Mar 2, 2026
A final change order would cut the Oak Hill water system improvements project cost by $55,346.80, funded through federal ARP money.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Portland
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.