Dry Creek Commons incomplete improvements
Summary
The developer got another year on its $125,000 performance bond, with 26 of 39 townhouse units done. The bond keeps the city protected if paving, landscaping and sidewalks aren't finished.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.
Impact analysis
The $125,000 bond stays in place another year rather than being drawn down or increased.
The developer gets more time; neighbors get assurance the road and sidewalk work will be finished.
Homeowners waiting on final paving, sidewalks, and landscaping if work drags on.
Mentions & discussions (3)
Planning Commission - Oct 5, 2026
The developer got another year on its $125,000 performance bond, with 26 of 39 townhouse units done. The bond keeps the city protected if paving, landscaping and sidewalks aren't finished.
Planning Commission - May 4, 2026
The 62-unit townhouse phase is 100% built, but final paving, sidewalks, stormwater features and sewer testing remain — and construction damaged roadway asphalt, curbs and sidewalks. The bond keeping the developer on the hook was extended one year.
Planning Commission - Jan 5, 2026
The townhouse development still has unfinished sidewalk sections from concrete problems during installation. The developer got one final year on its $40,000 bond to finish the roughly $20,000 of remaining work.
Related development
Dry Creek Commons Phase Two
The extension keeps the city's financial protection in place while the developer finishes the last of the infrastructure.
Cedar Side at Dry Creek Section Two
The extension gives the developer until mid-2027 to finish streets, sidewalks and stormwater work while the bond protects the city and homeowners.
Dry Creek Commons Phase 1
Residents should see the remaining sidewalk fixes completed within the year; the developer has no more chances for extensions.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Goodlettsville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.