White Rock Tower access road cost overruns

Summary

The road project to reach the White Rocks radio tower site ballooned by $855,800 — from about $488,700 to $1.34 million — after unstable roadbed and contractor work done without authorization drove costs up. Commissioners approved the change order anyway to finish delivering tower equipment.

At a glance

Total mentions
3
Last 30 days
0

Last discussed Aug 17, 2026.

Impact analysis

💰Financial impact

Adds $855,800 to the project — nearly tripling the original bid — with $602,877.81 from ARP funds and $252,923 from fund balance.

✅Who benefits

Emergency communications improve once the tower site is reachable and radio equipment is installed.

⚠️Who could be affected

Taxants absorb the overrun, and the engineer's letter suggests the contractor performed work without authorization — a cost-control concern.

Mentions & discussions (3)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Carter County

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.